List of properties

 
PlaceForm of
ownership 1
Ownership share in %Year of constructionYear of refurbishmentPlot area m2Residential m2Office in m2Retail in m2Hotel/catering
in m2
Storage in m2Miscellaneous in m2Total rentable area in m2Total no. of parking spaces
Investment properties              
Zug City Center site              
Baarerstrasse 20–22 (Metalli I/II, Zug Estates share)ZugCO72.251987/199116 4198 17012 16917 8868624 37790544 369519
Baarerstrasse 14a (Metalli III)ZugSO10019954 8432705 3253 08603 626012 307121
Industriestrasse 13a/c (Metalli IV)ZugSO10019952 1551 9651 63438146170805 14993
Industriestrasse 16 (leasehold) 2ZugLHP1003 200
Industriestrasse 18ZugSO10019921 63701 7130036002 07330
Haldenstrasse 12–16 (Haldenhof)ZugSO10020093 6153 1480000593 20754
Residential development Haldenstrasse/MetallstrasseZugSO1001910–19911986–198913 4738 22200011388 27168
Total Zug City Center site     45 34221 77520 84121 3531 3239 0821 00275 376885
Suurstoffi site              
Suurstoffi 3–5, 9, 13–17RotkreuzSO1002011/201219 37014 54600001914 565282
Suurstoffi 7, 11 (Alte Suurstoffi)RotkreuzSO100ca. 192620122 680000005205200
Suurstoffi 8–12 (construction site 5, buildings A+B)RotkreuzSO100201311 96110 0943 59000159013 843311
Suurstoffi 14 (construction site 5, buildings C)RotkreuzSO10020132 29008 1770044808 62537
Suurstoffi 41RotkreuzSO10020146 43005 9880048906 47765
Total Suurstoffi site Other     42 73124 64017 755001 09653944 030695
Other              
Hofstrasse 1a/bZugSO10019712 806503698003301 23429
Rote Trotte 14–16BaarC10020071 687718000010582310
Industriestrasse 8OberentfeldenSO1001956197420 55101 21201416 0946 45713 904105
Total other     25 0441 2211 91001416 1276 56215 961144
Total investment properties (excl. properties under construction)     113 11747 63640 50621 3531 46416 3058 103135 3671 724
Investment properties under construction             
Suurstoffi West (construction site 3)RotkreuzSO1002014/201518 77010 3120000010 312413
Total investment properties under construction  18 77010 3120000010 312413
Undeveloped plots           
Suurstoffi siteRotkreuzSO10042 539
Total undeveloped plots     42 539
Total real estate portfolio 3     174 42647 63640 50621 3531 46416 3058 103135 3671 724
Operating properties 34ZugSO/C10012 8711 879860013 002277016 018178
Total Portfolio     187 29749 51541 36621 35314 46616 5828 103151 3851 902

Additional information

in CHF thousands or %Book value
31.12.2014
Book value
31.12.2013
Projected
rental revenue
31.12.2014
Projected rental revenue
31.12.2013
Vacancy rate
31.12.2014
Vacancy rate
31.12.2013
Zug City Center site, Zug621 948584 58728 87327 1101.61.7
Suurstoffi site, Risch Rotkreuz255 738227 09012 65411 13311.55.6
Other22 59024 1901 4321 5150.50.4
Investment properties900 276835 86742 95939 7584.42.7
Inv. properties under construction, at fair value77 46035 640
Inv. properties under construction, at production cost17 31111 383
Undeveloped plots9 2699 269
Total real estate portfolio1 004 316892 15942 95939 7584.42.7
Operating properties 139 09041 045
Total portfolio1 043 406933 204

Additional information on Suurstoffi development project, Risch Rotkreuz

Project description
A mixed-use development with approx. 150 000 m2 GFA is to be built in several phases on the Suurstoffi site (approx. 100 000 m2) near Rotkreuz railway station. The development will, essentially, become part of the Group portfolio.

During the first phase, completed in spring 2013, around 13 000 m2 of commercial space and 228 rental apartments were created. In a second development phase, with an investment volume of approx. CHF 100 million, an office building with approx. 6 000 m2 of rental space was completed in mid-2014 and 156 apartments are close to completion.

Project status
The first construction phase has been completed, The second construction phase is about to be completed. The construction of the office block (around 6 000 m2 of rental space) was started in  April 2013 and successfully completed in summer 2014. SIS Swiss International School rents additional space here. In July 2013, work commenced on the construction of nine apartment blocks with a total of 145 rental and 11 owner-occupied apartments. The construction of the residential properties will be completed shortly and the apartments will be handed over to the residents in spring 2015.

 
in % 31.12.201431.12.2013
Occupancy level by floor area (commercial units) or number (residential units) 
Suurstoffi 41 (office building east)4545
Suurstoffi 19–35 (construction site 3)10030
Completion 
Suurstoffi 41 (office building east)completed
Suurstoffi 19–35 (construction site 3)Spring 2015

Quick Finder